No new photos today. I will have some soon though. In the coming week the dining room floor will be complete, the furniture and tables will be installed, the bar will be installed, the kitchen exhaust system and appliances will be installed and the kitchen floor tiled. Then we can get the finish work done in the dining room.
As this is all going on our external grease trap and the new sewer lin to the building is being installed. Then they will be able to pave the back parking lot. Then the sidewalk will be rebuilt out front.
The back lit restaurant sign will be installed next week.
So once things move along a little bit further I will post some new phoos.